NET EXAM Software Engineering Previous Years Questions


Reference Book for Software Engineering

1.      Which one of the items listed below is not one of the software engineering layers?         
(Jun - 2011)
A.     Process
B.     Manufacturing
C.     Method
D.     Tools
Answer: - B
2.      What is the first stage in program development? (Jun – 2011)
A.     Specification and design
B.     System Analysis
C.     Testing
D.     None of the above
Answer: - B
3.      By means of a data flow diagram, the analyst can detect            (Jun – 2011)
A.     Task duplication
B.     Unnecessary delays
C.     Task overlapping
D.     All of the above
Answer: - D
4.      Which of these are the 5 generic software engineering framework activities?(Jun – 2011)
A.     Communication, planning, modeling, construction, deployment
B.     Communication, risk management, measurement, production, reviewing
C.     Analysis, designing, programming, Debugging, maintenance
D.     Analysis, planning, designing, programming, testing
Answer: - A
5.      Many causes of the software crisis can be traced to mythology based on(Jun – 2011)
A.     Management Myths
B.     Customer Myths
C.     Practitioner Myths
D.     All of the above
Answer: - D
6.      For a data entry project for office staff who have never used computers before (user interface and user-friendliness are extremely important), one will use    (Dec – 2011)
A.     Spiral model
B.     Component based model
C.     Prototyping
D.     Waterfall model
Answer: - C
2.      An SRS                        (Dec – 2011)
A.     Establishes the basis for agreement between client and the supplier
B.     Provides a reference for validation of the final product.
C.     Is a prerequisite to high quality software?
D.     All of the above.
Answer: - D
7.      McCabe’s cyclomatic metric V(G) of a graph G with n vertices, e edges and p connected component is             (Dec – 2011)
A.     E
B.     (B) n
C.     (C) e – n + p
D.     (D) e – n + 2p
Answer: - C
8.      Emergency fixes known as patches are result of                         (Dec – 2011)
A.     Adaptive maintenance
B.     perfective maintenance
C.     Corrective maintenance
D.     None of the above
Answer: - C
9.      Design recovery from source code is done during                      (Dec – 2011)
A.     Reverse engineering   
B.     Re-engineering
C.     Reuse   
D.     all of the above
Answer: - D



10.  Following is used to demonstrate that the new release of software still performs the old one did by rerunning the old tests:                 (Dec – 2011)
A.     Functional testing
B.     Path testing
C.     Stress testing   
D.     Regression testing
Answer: - D














No comments: